The Church of Our Savior multi-purpose building continues to take shape. Recent activities:
• The fire sprinkler system was installed and passed a pressure test on Friday, 23rd of June.
• The curbs have been installed throughout the road and parking lot. (See adjacent photo.)
• Sidewalk forms have been constructed for pouring starting Tuesday, 27th of June.
• Sheet rock has been installed on the first floor and electrical, A/C and lighting infrastructure are also in place.
• Sheet rock and insulation can be see being lifted to the second floor via the crane in an adjacent photo.
At this point there are no critical issues preventing completion of the construction during August. Windows and doors have not yet been delivered, but this is not viewed as a major obstacle.

The crane opposite the building’s east wall is loading sheet rock and insulation to the second floor.