Posted by Kent Steen

In general, the Church of Our Savior Multi-purpose building at 2092 Beach Boulevard is at the end stages of construction and approximately on schedule. The estimated completion date is by the end of August (current month) assuming all continues to go well. A major milestone was achieved on 1 August when Beaches Energy Service connected power to the building. Having full power will make every aspect of inside sub-contractors’ tasks much easier in addition to providing better lighting and air conditioning. Further, the engineered wood flooring for the sanctuary will be able to “cure” properly before being laid.
Other activities:
Lampposts for the parking area are being installed
Grading in preparation for the parking lot asphalt to be laid is almost finished (See adjacent photo)
Interior walls are being painted
The six foot white fence bordering adjacent property has been installed
The South lot has been cleared of excess brush
The exterior is in the process of being painted. See adjacent photo)

Looking North from the entrance to the multi-purpose building

Building Exterior on 3 August