Posts

Kent Steen
March 23, 2017

Multi-Purpose Building Foundation is in Place

Our building program met another milestone this week when our foundation was poured. We are on track with the construction schedule as published, with an end summer finish date. In the coming days we will see the walls erected for the first floor. Of interest, the walls are ICF or Insulated Concrete Forms. The cavity […]

March 4, 2017

Site work continues, building schedule on track.

At the site The month of February witnessed the preparation of our building pad to receive the foundation. Importantly, our Building Permit was issued at the first of the month by the City of Jacksonville Beach. During the month General Contractor (GC) and our building team dealt with two separate initiatives from the City of […]

January 22, 2017

Major fill work completed at our building site

The photo shows the condition of our building lot on 21 January. (We are looking west.) The first phase of the site preparation is nearing completion. The next phase will involve installing the new water main on behalf of the city. This work should be undertaken this week. The pads for the foundation for the […]

January 7, 2017

Kicking Off 2017 by Clearing our Building Site

Happy New Year! We start our long awaited site improvement and building progress the first week of January, 2017 with our contractors removing trees from the building site at 2092 Beach Boulevard. (Please see pictures of the progress below taken by Bill White.)  We expect to have a fence across the public driveway leading to […]

December 23, 2016

Building site clearing and preparation to start early January, 2017

At last, the site and tree clearing permit has been issued by the City of Jacksonville Beach. This action clears the way for work to actually begin on the church’s building site at 2092 Beach Boulevard.  The first action will be to place an opaque fence across the public driveway leading to the lift station […]

December 5, 2016

Major Building Program Milestones

In a major milestone, on December 1st, Church of Our Savior closed on a loan of $1.25 Million through the generosity of Holy Trinity Anglican Church of Fernandina Beach.  At the same time we paid off previous mortgages held by the former owners on the remaining two building parcels.   Last week the site clearance permit […]

November 28, 2016

City of Jacksonville Beach approves Church of Our Savior Site Development Plan

On 28 November 2016, Church of Our Savior received formal notification that our Site Development Plan had been approved by the City of Jax Beach.   Individual Departments within the city requiring approval included electrical, public works, police, fire, and the planning department.  With this approval we are able to go forward with other required permits […]

November 1, 2016

“Final” Rendering of CoOS Multi-Purpose Building

We have approved the final design of the multi-purpose (MP) building to be erected during Phase I of the Church of Our Savior building program.  See rendering below. The design has been reworked to reflect a change in the mission of the building to that of interim primary worship space in addition to administrative and […]

October 18, 2016

Revised Elevations for Multi-Purpose Building

The leadership of Church of Our Savior has determined that our best course of action is to build our multi-purpose (MP) building in phase I instead of the Chapel.  This decision was made due to the unanticipated growth in costs driven by the current building boom in our area.  More specifically, there is a shortage […]

October 18, 2016

Tim Young of Tim Young Construction selected as the General Contractor for site preparation and construction of CoOS Multipurpose Building

The architecture team has selected Tim Young to go forward with our Phase I construction work.  This effort will include site preparation and construction of our Multipurpose Structure. We welcome Tim, formerly of E.C. Kenyon Construction Company, Inc. and look forward to having him lead our construction effort.

Page 1 of 3