August 18, 2017

Church of Our Savior; Building Progress Update, August 18, 2017

The building process at 2092 Beach Boulevard, the site of our new multi-purpose building, is on pace for an end-August conclusions. We will begin the transition to the building when we get the various government sign-offs starting in September. Tentative plans call for transition from Malone Hall and the delivery of sanctuary furniture and fixtures […]

August 9, 2017

Construction Enters its Last Month

Construction Schedule – Church of Our Savior 8-8-17Construction of the Church of Our Savior multi-purpose building proceeds on schedule. The adjacent photographs taken midday on 9 August, show the exterior of the new building in the late stages of construction. Note that the building now has its final coat of paint. The front door, to […]

August 2, 2017

2 August, 2017 Building Progress Update

In general, the Church of Our Savior Multi-purpose building at 2092 Beach Boulevard is at the end stages of construction and approximately on schedule. The estimated completion date is by the end of August (current month) assuming all continues to go well. A major milestone was achieved on 1 August when Beaches Energy Service connected […]

July 11, 2017

July 11 Bullets from the Building Site

In general, our new building is proceeding according to the construction schedule and should be completed by the end of August, 2017. Some current activities: • As seen in the adjacent photo, stripping to hold the insulation and exterior trim is being applied to the external wall. • The installed sheet rock on the first […]

June 26, 2017

Church of Our Savior Building Construction Notes from 26 June, 2017

The Church of Our Savior multi-purpose building continues to take shape. Recent activities: • The fire sprinkler system was installed and passed a pressure test on Friday, 23rd of June. • The curbs have been installed throughout the road and parking lot. (See adjacent photo.) • Sidewalk forms have been constructed for pouring starting Tuesday, […]

May 26, 2017

Roof Takes Shape on Church of Our Savior Multi-Purpose Building!

The second floor Insulated Concrete Forms (ICF) walls have been erected and ready mix poured to complete the process. Pre-fabricated trusses for the roof have been lifted by a crane and fastened into place. The adjacent images show the building status on Friday, May 26, 2017. The inside pictures show a view of the trusses […]

March 23, 2017

Multi-Purpose Building Foundation is in Place

Our building program met another milestone this week when our foundation was poured. We are on track with the construction schedule as published, with an end summer finish date. In the coming days we will see the walls erected for the first floor. Of interest, the walls are ICF or Insulated Concrete Forms. The cavity […]

March 4, 2017

Site work continues, building schedule on track.

At the site The month of February witnessed the preparation of our building pad to receive the foundation. Importantly, our Building Permit was issued at the first of the month by the City of Jacksonville Beach. During the month General Contractor (GC) and our building team dealt with two separate initiatives from the City of […]

January 22, 2017

Major fill work completed at our building site

The photo shows the condition of our building lot on 21 January. (We are looking west.) The first phase of the site preparation is nearing completion. The next phase will involve installing the new water main on behalf of the city. This work should be undertaken this week. The pads for the foundation for the […]

January 7, 2017

Kicking Off 2017 by Clearing our Building Site

Happy New Year! We start our long awaited site improvement and building progress the first week of January, 2017 with our contractors removing trees from the building site at 2092 Beach Boulevard. (Please see pictures of the progress below taken by Bill White.)  We expect to have a fence across the public driveway leading to […]